How Long Does Solar Take on Long Island?

The install is the fast part. Here's the whole timeline, including permit times town by town.

By Steve Maroney, founder of Power House Home Energy · Updated October 2026

The short answer

Most Long Island solar projects take about 2–3 months from signing to turning the system on. Town permits take 2 to 8 weeks depending on where you live, PSEG Long Island approves the connection before install, and the install itself usually takes one day (one to two for large systems, two to three with a battery). After a final inspection, PSEG Long Island issues Permission to Operate and your system turns on. We handle every permit and every piece of PSEG paperwork.

The steps, start to finish

StepWhat happensTypical time
1. DesignSatellite roof and shade analysis, system design and your proposalStarts right away
2. PermitsWe file with your town or village building department2–8 weeks, by town (below)
3. PSEG Long Island approvalInterconnection approval, required before installAlongside permits
4. InstallPanels, wiring and equipment1 day (large systems 1–2; with battery 2–3)
5. Inspection and PTOFinal inspection, then PSEG Long Island's Permission to OperateYour system turns on

Permit times by town

Where you liveTypical permit time
Town of Smithtown3–5 weeks (village review boards can add a couple of weeks)
Town of Islip3–5 weeks
Town of Brookhaven4–6 weeks
Town of Huntington4–6 weeks
Town of Hempstead2–4 weeks
Town of Oyster Bay2–4 weeks
Town of North Hempstead6–8 weeks
New York City (all five boroughs)5–8 weeks with the NYC Department of Buildings, plus Con Edison approval
Westchester, Rockland, Orange, Putnam and Dutchess3–8 weeks, depending on the town or village
Babylon, Riverhead, the East End and Shelter IslandVaries by town and village; we give you the timeline for your address up front

Homes inside an incorporated village go through that village's building department instead of the town's. Historic districts, homeowners' associations and design review boards can add a review step, and we prepare the drawings and paperwork they ask for.

Install days, by project

Solar

One day for most homes; one to two days for large systems.

Solar with a battery

Two to three days.

New roof

A typical roof replacement takes one day, usually right before the solar install.

Heat pump

A heat pump install typically takes one day.

★★★★★

“Steve is an expert in his field and made it very easy to understand all of our options and go with what was best for us. The customer service term was a breeze to work with, including setting up the required inspections and paperwork. The installation was done expertly and in total only took a couple of hours. We love the slim look of the panels compared to others we have seen in our neighborhood. It's also a lot of fun checking the app to see the rates of energy being generated and delivered to the grid in real time. I would strongly recommend getting your solar from Power House.”

Mike · Islip, NY · Google review

What can slow things down

A village architectural review board or historic district review
Tree work that needs to happen before the install
A main electrical panel that needs an upgrade
Busy seasons at the building department or the utility

We file as early as possible and tell you about any of these up front, so there are no surprises.

Common questions

How long does it take to get solar on Long Island?

Usually about 2–3 months from signing to turning the system on. Town permits take 2 to 8 weeks depending on where you live, PSEG Long Island approves the connection before install, and the install itself usually takes one day.

How long does a solar installation take?

Most residential solar installs take one day. Large systems take one to two days, and systems with battery backup take two to three days.

How long do solar permits take in my town?

Typical times: Smithtown and Islip 3–5 weeks; Brookhaven and Huntington 4–6 weeks; Hempstead and Oyster Bay 2–4 weeks; North Hempstead 6–8 weeks; New York City 5–8 weeks; Westchester, Rockland, Orange, Putnam and Dutchess 3–8 weeks.

What is PTO?

Permission to Operate is the final approval from PSEG Long Island, or your utility, after inspection. Once you have it, your solar system can turn on and start saving.

Keep reading:What to expect during installation →Should I replace my roof first? →Areas we serve →How much does solar cost? →
Get Your Energy Review

Get your timeline and your numbers.

Let’s review your energy use, answer your questions and show you the options available for your home.